How data centre heat reaches the LNG
- Basis: estimates, yearly averages
- Coverage: about 92% of the heat the LNG needs, over a year
- Surplus: the campus offers more heat than the LNG can take; the spare heat goes to the dry coolers
- Backup: the gas burners cover the hours when the link is down
- Link: two buried pipes, about 2 km each way; closed water loop with pumps
- Safety: terminal inside its own safety zone, data centre outside it
- Campus heat: IT nameplate × 71% average draw × 90% captured in the liquid loop
- Terminal need: 6 Mt of LNG a year × 780 kJ per kg
- Link availability: 92% of the year, matched to the terminal; coverage stops at that share even though the campus offers more heat
- Gas no longer burned: that share of the 1.5% of each cargo the terminal deducts for its own use
- Loop flow: about 1.31 m³/s for a 27°C drop between the pipes
- LNG tankers avoided: 1.26 TWh a year of gas ≈ 1.1 average cargoes (81 cargoes, about 6 Mt, landed in 2025)
- Loop temperatures: as at Isle of Grain, UK, link opened 2012: up to 340 MW, water out at about 42°C and back at 15°C, two 4.5 km pipes of 1.2 m
- Data centre temperatures: current Nvidia direct liquid cooling designs, about 45°C supply
- Vaporizers at Świnoujście: submerged combustion; LNG tubes in a water bath heated today by a gas burner
Why US gas costs Poland 2 to 3 times the Henry Hub price
- Basis: author's model estimates, not official prices; euro per MWh of gas
- Contract price: 115% of Henry Hub plus a liquefaction fee of €7.7 (Orlen's own fees are not public)
- Shipping: €3.1
- Regasification: €1.75; grid entry: €0.5
- Henry Hub: €10.0 (13 Nov 2026; quoted in the US as $3.23 per MMBtu)
- Exchange rate: $1.1052 per euro
- Red slice: Gaz-System's published LNG consumption rate, 1.5% of every cargo, deducted for the terminal's own use; all of it treated as gas burned to warm the LNG; metered figure not found
- Campus effect: a 250 MW campus removes about 92% of the red slice
- Best Orlen contract (estimate): lowest reported liquefaction fee, €5.4 (Venture Global's first Calcasieu Pass contracts); shipping €1.5 on Orlen's own fleet
- Spot in Germany: €92.43 (Trading Economics, German THE gas, 13 Nov 2026)
- Texas industrial gas: about €8.9 (EIA, August 2026); a different month from the Henry Hub quote, so the small gap between them means nothing
- Power tile: new gas plant at 55% efficiency
- Power tile, Europe: gas at the pre-crisis €30 (S&P Global, TTF broke below EUR 30 in late November 2025; Dutch TTF hub, which German prices track closely); carbon €80 per tonne (about EUR 80/t in late November 2025 (GMK Center, Rabobank))
- Power tile, Texas: gas €11.3 (EIA, November 2025, USD 3.81 per Mcf); no carbon price
- Contract mix: most Polish long-term LNG contracts are Henry Hub indexed; more than a third of 2025 volume was bought spot at market prices, so the spot-to-contract gap applies only to contract cargoes
- Who keeps the gap: inferred from contract pricing, not from published accounts
- Check: regulator's average declared price for gas imported from outside the EU, about €29 to €32 per MWh, first half of 2026
Has anyone done this?
- Data centre in such a loop: none known (November 2026)
- Idea first proposed: US start-up TeraCool, 2012 to 2014
- Isle of Grain bar: the most its link can carry, up to 340 MW
- Barcelona bar: yearly average from the 131 GWh a year its partners report
- Świnoujście bar: yearly average, author's model: 250 MW campus × 71% average draw × 90% captured in the liquid loop = about 160 MW offered; the LNG takes up to its average need of 148 MW; link running 92% of the year
How shared savings impact economics
- Basis: author's model estimates, not official numbers
- Cost of 1 MW a year: servers €23.6 million per MW over 5 years; facility €10.6 million over 15 years; other costs €0.4 million a year; electricity at 71% average utilisation
- Cost model: central values follow Epoch AI's May 2026 model (stylised, not a project budget)
- Power, Texas and Finland: €65 and €81 per MWh, whatever the European gas price
- Power, Poland at the 2024 level: €96.3 wholesale (2024 day-ahead average, PLN 424.94) + €14.6 levies = €111 before network charges, whatever gas costs; held there because solar and batteries push prices down
- Power, Poland at the 2027 forward: €128.8 (BASE_Y-27, October 2026, PLN 568.11) + levies = €143
- Power, rushed Texas campus on its own gas turbines and engines: €109 per MWh, range €86 to €149 (Rabobank, BloombergNEF and SemiAnalysis, 2026: $100 to $170 per MWh; spare units for reliability and a 5 to 10 year write-off); same servers, capital and PUE as the Texas grid campus
- Power, Texas on rented mobile turbines: about €285 per MWh, range €208 to €362 (CBRE, November 2026: $230 to $400 per MWh)
- Capital, Texas and Finland: always 8%
- Capital, Poland state-backed: 60% euro debt at 4.5% (Poland's ten-year euro bonds yield about 4.3%) + 40% equity at 10.5% = about 6.4% after tax
- Terminal saving: gas no longer burned (1.5% of each cargo deducted today, assumed fully avoidable for the share the campus covers) + carbon allowances at €88 per tonne
- Heat link: €100 million over 15 years at 6.5%, paid first out of the saving; only the rest is shared
- Cooling: the data centre saves a little cooling electricity in every scenario, so Poland's cost falls slightly even when all of the saving goes to gas shippers
- Heat price benchmark: Stockholm Exergi (Stockholm's district heating company) indicates roughly €21 per MWh for data centre heat (author's conversion, heat delivered all year)
Months from decision to first power
- Memphis: 122 days inside an existing factory, on portable gas turbines (Shelby County first treated them as portable and outside permitting; at the Colossus 2 site next door they stand on trailers); outer bound, not a model to copy
- Abilene: about 16 months to the first 100 MW, about 19 months to about 200 MW (Epoch AI)
- EU: 18 months, the EuroHPC tender condition for an AI gigafactory's first phase
- Poland today: 49 months average (Polish Data Center Association, PLDCA), about 25 of them waiting for decisions, appeals and approvals
- Poland with a special act: 18 months, author's target, not a forecast; no Polish data centre has been built under a special act
- How 18 months: the act removes most of the 25 months of waiting; a site prepared before the tender by Gaz-System (land, heat link, grid connection, permits) lets construction start at once and take about as long as at Abilene
- Western European hubs: 7 to 10 years for the grid connection alone (Interface think tank, reported by Euronews, May 2026)
- Value of one month earlier: €0.12 million per MW while AI capacity is scarce, range €0.04 to 0.35 million (low: what developers have paid to get power sooner; high: Morgan Stanley's and Carnegie's models)
- Idle servers waiting for power: about €0.6 million per MW per month
- Second chart: 10 years of the yearly cost of 1 MW of AI compute (servers, building, staff, power, as in the savings chart) + €0.12 million per MW for each month of waiting beyond 18 months
- Poland with a special act: heat link, saving split half and half, 2027 forward gas price; Poland today: no heat link; both: grid power at the 2024 price level
- Texas break-even: about 25 months; at 26 months a Texas campus costs more than Poland with a special act
- Amsterdam: €106 per MWh (Eurostat, largest industrial users, first half of 2026, excluding VAT); PUE 1.13; 102 months, the middle of the 7 to 10 year grid wait
Sources
- APR Energy: Latitude Media, 15 July 2026 (bought by Elon Musk, deal closed mid-May 2026, about $1 billion, mobile gas turbine fleet)
- Model: model.mjs (run it with Node, it prints every table) and assumptions.csv (central, low and high values with sources).
- Polish Radio: Tusk in Sopot on technological sovereignty
- bne IntelliNews: Tusk in Choczewo on offshore wind and data centres
- PAP: Poland signs the AI gigafactory agreement
- Implement Consulting Group: The economic opportunity of generative AI in Poland
- Ember: European wholesale electricity prices
- Epoch AI: AI data centre cost breakdown
- Gaz-System: LNG terminal technical data and regasification tariff
- Orlen: 2025 LNG deliveries; Bankier: almost 6 million tonnes
- Isle of Grain heat link: Process Engineering, Modern Power Systems
- Dunkerque LNG: Fluxys; Barcelona: Veolia
- TeraCool: IEEE Spectrum, 2014, Data Center Knowledge, 2013
- Belarus border barrier: MSWiA, 30 June 2022, Sejm vote, Polsat News; Balcerowicz plan: Wikipedia; Baltic Pipe: Gaz-System; KCPD act: KPMG
- Zeebrugge: IIF-IIR, LNG 12 conference paper; Polish gas supply in 2025: Globenergia
- Sejm: energy committee sitting 43, 5 December 2024; grid act of 13 March 2026; LNG terminal act
- Świnoujście vaporizers and sea temperature: Inżynieria.com on the expansion, Polskie LNG, 2017 Seveso workshop slides, Bulletin of Geography, 2019
- Power and gas prices: TGE, October 2026 summary, Modo Energy on Polish coal costs
- Cost of capital: Poland's euro bonds 2030 and 2036, CoreWeave notes
- Campus size: Epoch AI, largest AI data centres, Nebius Lappeenranta
- EuroHPC: AI gigafactory call and deadlines; UKAEA: Culham expression of interest
- Dolna Odra: Ministry of Energy reply of 28 August 2026; Ministry of State Assets replies of 22 October 2025 and 23 September 2026
- Choczewo: climate ministry, first offshore power, July 2026; Dolna Odra coal units: Biznesradar
- Gramwzielone: data centre connection queue, Gryfino battery
- URE: offshore wind auction
- Rzeczpospolita: the race for AI gigafactories
- West Pomerania: data centre siting study
Disclosure
- Financial interest in the terminal, Gaz-System, Orlen or any data centre operator: none
- Exchange rates: PLN 4.41 and USD 1.105 per euro (ECB, 13 November 2026)